← BACK TO PROJECTS PRJ-2026-04 // COMPLETED

I-90 CORRIDOR VIADUCT EXPANSION.

Design-build reconstruction and two-lane widening of a 1.8-mile elevated interstate viaduct over active rail freight corridors with zero unscheduled traffic closures.

I-90 Corridor Viaduct Expansion concrete piers and steel superstructure under crane erection
CLIENT
Illinois DOT
LOCATION
Chicago, IL
CONTRACT VALUE
$64.5M
DURATION
24 Months
STRUCTURAL SYSTEM
Post-Tensioned Box Girder
SAFETY RECORD
0.00 LTI / 420k Hrs
01 / PROJECT CHALLENGE

ACTIVE INTERSTATE & FREIGHT RAIL CONSTRAINTS

The existing I-90 viaduct carried 148,000 vehicles per day across an active Class I freight rail yard and soft lacustrine clay strata extending 75 feet to bedrock. Illinois DOT mandated maintaining four continuous lanes of live interstate traffic while eliminating substructure settlement risks and meeting strict winter freeze-thaw curing specifications.

02 / ENGINEERING EXECUTION

STAGED DRILLED SHAFTS & BALANCED CANTILEVER ERECTION

STRATA engineered a phased foundation program installing 142 rock-socketed drilled shafts using low-headroom hydraulic rigs adjacent to live rail tracks. Precast post-tensioned segmental box girders were erected via overhead launching gantries during nocturnal 4-hour rail windows, accelerating deck completion by 11 weeks ahead of the baseline CPM schedule with zero lost-time incidents.

BILL OF MATERIALS

KEY QUANTITIES

Structural Steel 4,800 Tons
High-Strength Concrete 18,500 CY
Deep Foundation Piles 142 Units
Post-Tensioning Strand 310,000 LF
Reinforcing Rebar 2,940 Tons
Total Craft Hours 420,000 Hrs

QA/QC AUDIT: 100% AASHTO & IDOT SPEC COMPLIANCE

03 / SITE DOCUMENTATION

FIELD EXECUTION RECORD

Pier erection and structural steel scaffolding
FIG 01 — PIER ERECTION
Viaduct deck pour and heavy crane steelwork
FIG 02 — DECK POUR
Aerial inspection and final structural load test
FIG 03 — FINAL LOAD TEST